Fern
- 01
The problem
Engineering changes quietly blow up budgets and schedules. Open POs, scrapped inventory, rework and supplier lead times don’t get priced in until after the change is approved.
- 02
The solution
A multi-agent system (Claude Agent SDK, MCP) reads the ECR from PLM, computes the BOM delta, and runs cost, timeline and Monte Carlo lead-time models against ERP data in about 60 seconds. Agents only extract and explain; code computes every number, each tagged with its evidence class.
- 03
Real example
An engineer files a change for a cracked motor-controller bracket. Fern prices it at +$415 per aircraft plus $142K–$156K one time, and flags that the only qualified supplier’s 14-week lead time puts the change on the line 13 weeks late, before the board approves it.